Port Phillip Council has avoided the budget blowouts hitting state and federal governments, lifting its projected surplus to $0.75 million despite a tough economic climate.
Council has endorsed its first-quarter 2026-27 financial review, which shows a modest improvement in the bottom line.
Officers credited tight cost control and strategic adjustments, while extra funding was approved for local community assets.
Thin surplus, but stable
The cumulative cash surplus – council’s key measure of financial sustainability – is now forecast at $0.75 million, up from the $0.67 million adopted in June 2026. It is a marginal but welcome gain of $0.08 million.
Efficiency savings of $1.22 million, from developer negotiations, organisational realignments and external grants, drove the result. Supplementary rates revenue from completed developments added $0.80 million, and extra state government funding for maternal and child health services contributed $0.29 million.
The gains offset several headwinds: a $0.65 million provision for a localised review of award wages interpretation, $0.12 million in agency staff to cover educator vacancies at long day care centres, and rising pressure on local laws and freedom of information services.
Despite inflation, fuel shortages and a tight recruitment market, Port Phillip still expects a ‘low risk’ financial sustainability rating under Victorian Auditor-General’s Office (VAGO) indicators.
Major budget adjustments and project ‘rephasings‘
Council also approved a string of adjustments and rephasings (that’s council speak for delays), including:
Elwood Main Drain works: An $11 million contribution from Melbourne Water temporarily pushed the net result indicator to 14.7 per cent. The money is earmarked for the drain works, which will be delivered over the coming financial years.
Smith Street streetscape redevelopment: Delays in Fishermans Bend Development Contribution Plan funding have pushed $1.78 million in revenue and expenditure into 2027/28.
South Melbourne Town Hall: A further $0.80 million for works, drawn entirely from the Asset Renewal Reserve.
Bay Trail footpath: $407,000 was approved following detailed design to fix safety, compliance and asset condition issues, including widening the path and adding concrete edge strips.
Palais Theatre tunnel: $672,000 from the Palais Theatre reserve will address structural risks and slab defects.
St Kilda Botanical Gardens public toilets: $380,000 from the Asset Renewal Reserve will complete the works after post-tender reviews.
Urgent budget requests approved
Council also approved three urgent, unbudgeted requests for 2026/27:
1. EcoCentre weekend support ($17,000): Extends weekend opening hours from 1 April to 30 June 2027. Long-term funding will be assessed in the next budget cycle.
2. Port Melbourne Bowls Club ($50,600): Matched funding to cover a budget overrun on the clubhouse upgrade.
3. Integrated Transport Strategy ($100,000): Funds brought forward from 2027/28 to start deliberative community engagement immediately.
Emerging risks on the horizon
Chief financial officer Peter Liu and general manager Robyn Borley warned of significant medium-term risks.
Chief among them is build-to-rent. The developments are exempt from open space contributions, which has already cost up to $17 million in forgone revenue needed to fund public parks. Childcare utilisation is also weak, at 62 per cent against a 66 per cent target.
Even so, the CEO and CFO concluded a formal revised budget is not required, leaving Port Phillip on a steady, fiscally disciplined path.
An additional mobile CCTV trailer will also be added, meaning two mobile units will be available for local deployment.
But wait, there’s more …
Also tabled at the council meeting was the CEO’s report, which flags a string of emerging problems.
The CEO’s report (Issue 132 – Quarter One Review 2026/27) identifies several projects as off track or at risk, along with performance measures below target and project delays that council might prefer not to highlight.
Major initiatives and projects: off track or at risk
Port Melbourne netball infrastructure project (off track): Delays in key procurement milestones for the clubhouse construction contract have put pressure on the delivery program. The tender evaluation was completed, but no contractor was appointed because tendered costs exceeded the available budget and raised value-for-money concerns.
Carlisle Street carparks strategy (at risk): The project has been delayed by 12 months amid ongoing negotiations over the extent of a future easement at the rear of Carlisle Street. It will remain at risk until all legal documentation, including a deed for rear access and a contract of sale, is finalised.
Library action plan and library network (at risk): The overall program is considered at risk. Following a refreshed Library Action Plan, endorsement of the Community Infrastructure Plan and identified infrastructure needs in the Lakeside/Domain ward, a revised business case is being prepared to focus on the library network as a whole.
Act and Adapt Sustainable Environment Strategy and Climate Emergency Action Plan (at risk/off track): While 81 per cent of actions were on track or complete, that fell below council’s 90 per cent target. Ten per cent of actions were ‘at risk’ and 4 per cent were ‘off track’.
Municipal flood modelling project (delayed): Delays outside council’s control have pushed expected completion to early 2027.
Blessington Street road construction (deferred): Planned works have been deferred for 12 months to allow for a broader streetscape and place-making review.
Road resurfacing renewal program (delayed sections): Work on Jackson Street and Albert Street has been delayed by the need for external investigations, approvals and underground surveys.
Performance measures below target
Several service performance measures fell well short of their targets in the first quarter:
Strategic planning referrals: Only 43 per cent were completed within required service levels, against a target of 80 per cent. Just three of seven referrals were finished on time because of the complexity of the planning matters.
Land information certificates: Only 74 per cent were issued on time, well short of the 90 per cent target and down from 97 per cent in the same period last year.
Childcare centre utilisation: Long day care utilisation remains weak at 62 per cent, short of council’s 66 per cent target.
Financial and operational challenges
The first-quarter review also identifies systemic and external pressures that pose ongoing risks to council’s financial sustainability and project delivery:
Build-to-rent open space exemptions: A growing number of build-to-rent developments are not required to pay open space contributions, limiting funding for public parks.
Cost shifting from planning reforms: Council had to allocate $105,000 of its own budget to adjust systems and processes to meet new state planning reform legislation.
Escalating project costs: Tenders and cost plans are consistently coming back well above original budgets.
Competitive resource market: Council is competing for design, construction and project management resources against the state government’s ‘Big Build’ and neighbouring councils.
Service pressures: Rising volumes and complexity of freedom of information (FOI) applications are requiring more resourcing and legal spending.